Duran Excavating 2007 Projects

Kearney Street Realignment

Duran Excavating, Inc. was awarded the Kearney Street Realignment project by the City of Commerce City. The project includes removal of asphalt, curb and gutter, fence and relocation of fence. Also included is clear and grub site, earthwork, storm sewer, sanitary sewer and water line. Construction of approximately 1,280 LF of new roadway. Including curb and cutter, inlets and asphalt.

New Academic Village

 

Duran Excavating, Inc. is the Subcontractor on this project. The General is The Whiting Turner Contractor. The project consists of the following: Site Demolition, Fine Grade, Detention Pond, Site Drainage, Bio Swales, Underdrains, Storm Sewer, Inlets, Relocating Waterline. This project will be completed by June 2007.

Waterline Evans

 

Duran Excavating, Inc. was awarded this project by The City of Evans. The project started May 28, 2007. The job consists of installation of approximately 5,947 linear feet of new 12-inch PVC water line, 388 linear feet of new 8-inch PVC water line and 10 linear feet of new 8-inch ductile iron water line. Installation of both 8” and 12” gate valves. Installation of approximately 12 new exterior water service meters. Installation of four Pressure Reducing Valve (PVR) stations.

SH – 66 St Vrain Bridge

As the General Contractor Duran Excavating, Inc was awarded this project by Colorado Department of Transportation. The project consists of the following: Clear and Grub, Strip Stockpile Wetlands, Install Temporary Diversion Pipes, Erosion Control, Realignment of River, Rip Rap, Reinstall wetlands, fencing, seeding, landscaping, Reinstall 66’ of RCP and Traffic Control.

Sanitary Sewer Improvements

 

As the General Contractor Duran Excavating, Inc. was awarded this project by the City of Greeley. This project will take place in two locations the 900 block of 12th and 13th. Avenue. Description of work consists of installing 8” PVC Sewer Main, Manholes, and Sewer Services. This work is located in existing roadways which also required Traffic Control and Asphalt Patching.

Nelson Road Improvements

The City of Longmont awarded Duran Excavating, Inc. this project as the General Contractor. This project started September 4, 2007. This project consists of Removal of asphalt pavement, Excavation, Embankment, Subgrade, prep Asphalt paving, Concrete flatwork, New storm sewer system 18”-42” RCP, Waterline installation, and Earthwork. The project is located along Nelson road which required difficult traffic control.

 

Adams Avenue Mead

The Town of Mead is the owner of this project and awarded it to Duran Excavating Inc. as the General Contractor. The start date was August 13, 2007. The job consists of Road Improvements, Grading, Asphalt, Storm Sewer, Inlets, and Constructing a Pond.

Rocky Mountain Metropolitan Airport – Schedule I and Schedule II

The Rocky Mountain Metropolitan Airport is located at 11755 Airport Way in Broomfield Colorado. The Airport is between the cities of Denver and Boulder. As the General Contractor Duran Excavating, Inc. was awarded this project by CH2M Hill. This project consists of Relocation of Taxiway A, which consists of grading Safety Area Runway 11 L/29R. The project includes: Milling, Asphalt, Grading for taxiway, Cement treated sub grade, Geotextile fabric, Base course, Bituminous paving, Under drain, 48” Storm Sewer, Inlets, Electrical, and Seeding. Extreme measure had to be taken for safety and traffic control in order to keep the existing Airport in operation. This project had to be constructed in 4 different phases which required a very short construction schedule. Many overtime hours were required along with weekend work including Sunday.

Waterline Evans

 

Duran Excavating, Inc. was awarded this project by The City of Evans. The project started May 28, 2007. The job consists of installation of approximately 5,947 linear feet of new 12-inch PVC water line, 388 linear feet of new 8-inch PVC water line and 10 linear feet of new 8-inch ductile iron water line. Installation of both 8” and 12” gate valves. Installation of approximately 12 new exterior water service meters. Installation of four Pressure Reducing Valve (PVR) stations.

Auburn Estates Conservation Development

Duran Excavating, Inc. was awarded this project by Victory West Development. The development is a conservation development of 64.39 acres into 26 lots. This project was started May 22, 2007. Auburn Estates is located in Fort Collins. The job consists of Residential Infrastructure, 26 Home sites grading, curbs. Asphalt, Sanitary, Water, Storm, County Road Improvements, overlay, and Storm.

Fairbairn Mead